Community

current notifications

There are currently no notifications for 168 Walker Street.

Shutdown period

Please note the construction site will be closed from Thursday 25 January and will reopen on Monday 29 January.

On-site preparation, demolition and excavation work to prepare the site is now complete. Construction commenced in late 2021, the first stage is the substructure construction of the basement.

We recognise the works will have impacts on neighbours and we appreciate your continued patience.

We believe that when delivered, the building will be a great addition to a rapidly changing neighbourhood.

Our project will be constructed in accordance with North Sydney Council’s conditions of consent.

You can also contact us direct by emailing 168walker@aqualand.com.au or calling 1800 016 659

Expected construction schedule

Completed
Timeline arrow pointing right.
  • Site establishment and preparation works
  • Undergrounding electrical power lines along McLaren Street
  • Erecting hoardings
  • Demolition and removal of existing structures
  • Excavation works including removal of debris and excess materials from the site
December 2021 – mid 2022
Timeline arrow pointing right.
  • Substructure construction
Mid 2022 – late 2023
Timeline arrow pointing right.
  • Superstructure construction
  • Façade install
Mid- 2023 – mid 2024
Timeline arrow pointing right.
  • External Works
*Note the above timeframes are anticipated and subject to change

What to expect during works

Hours of works

Construction activities will be undertaken according to the conditions of North Sydney Council’s consent.

  • 7am–7pm Monday to Friday
  • 8am–1pm Saturday – no excavation works on Saturdays
  • No work on Sundays and Public Holidays
  • Out of hours work can be required by Council and the governing authorities to occur outside of the standard construction hours. This is generally to avoid impacts on traffic and public transport arrangements. Approvals are obtained from the appropriate authorities for each activity.

Upcoming site closure dates

Upcoming site closure dates below. Please note that there will be no construction site activities during the dates however, our site office will still be operating.   

  • 29 March to 2 April (both dates inclusive)
  • 25 April to 28 April (both dates inclusive)
  • 8 June to 11 June (both dates inclusive)

Access and truck movements

  • All access and truck movements will be undertaken in accordance with the approved Council conditions
  • During substructure construction stage, construction vehicles will enter and exit the site via the designated McLaren Street access points
  • Traffic and safety controllers will be in place where required
  • Pedestrian access will be managed by traffic controllers.

Construction mitigation measures

During the course of the works, our contractors will be implementing the relevant mitigation measures to minimise the impacts of noise, vibration, dust and general disruption.

Contact us

Should you have questions about on-site work, you can contact us on the details below:

Email: 168walker@aqualand.com.au | Phone: 1800 016 659